The green is ready…almost! Patience! Patience!

Updated: Apr 4, 2020


True Draw of Australia finished laying the artificial surface (carpet) in late June, but before the green can be used the general contractor needs to complete the concrete sidewalk, handicap walkway and final grading of the site. It’s difficult to predict when the green will be open, but hopefully the green will be ready for play by the end of July. Given the inordinate amount of rain in late resulting in several lost work days, it is remarkable that the green was able to be completed by this time.