top of page
Search
Writer's pictureeditor

Progress on new green construction

Updated: Apr 5, 2020



From the club president: The project is currently ahead of schedule. The sub-base (which you see in the pictures on home page) will be completed in anticipation of the arrival of the True Draw crew from Australia, a container with the surface materials from China and a container with the installation equipment from Connecticut all on site by mid-May. If the weather will cooperate, the new playing surface should be completed by mid-July and the final work around the green (sidewalk, handicap ramp, & parking lot pavement, striping and signage should be completed by early Aug.


4 views0 comments
bottom of page